Mobile Blackspot Programs

The Mobile Blackspot program is an Australian Commonwealth Government grants program funding the delivery of mobile telecommunications sites that aim to improve mobile digital connectivity across regional, rural, and remote Australia. Field Solutions has been awarded funding under MBSP5 to deliver two sites that will support Optus 5G/4G services – both are now built, and Optus 5G/4G is live.
Under Round 5A of the MBSP, Field Solutions Group was awarded six additional sites to build that will facilitate Optus 5G/4G services. Three of these sites are now built, and planning is underway to deliver the Optus 5G/4G service from them. Two will commence construction shortly, and all are expected to be live by October 2024. In addition, Fields Solutions Group, in partnership with Optus, will undertake two key connectivity trials, both of which will commence at the end of Q2 2024.

Project Deployment Timelines

MBSP5: FSG is extremely proud to have been the very first Mobile Network Infrastructure Provider under the Federal Government’s Blackspot Program to deliver these towers, which are now providing great coverage and service to the region using Optus 4G network.

Bundemar


Mullengudgery


If you have any questions, please don’t hesitate to email us at govprograms@fieldsolutions-group.com, and one of the gang will get back to you.

Federal Government Blackspot Round 5A – Mobile Network Infrastructure

State

Name

Site Status

Indicative Rollout Timeline

NSW

Collymongle

Site now stood. Power connected. Optus will undertake the Deployment Code Activity and deploy mobile equipment on site.

June 2024

NSW

Strathmore Road Dungalear

Site acquired. Power design underway. Power easement approval in progress. Optus to undertake Deployment Code activities.

June 2024

NSW

Borwon

Site now Stood. Power connected. Optus to undertake Deployment Code Activity and deploy mobile equipment on site.

June 2024

NSW

Bullarah

Site now Stood. Power connected. Optus to undertake Deployment Code Activity and deploy mobile equipment on site.

June 2024

NSW

Tellegra

Site acquired. Construction to commence on site in Q2 2024. Optus will undertake the Deployment Code Activity and deploy mobile equipment on site.

June 2024

WA

Talbot

Site Acquired. Build to commence shortly. Delays expected on power delivery.

June 2024

 

Collymongle Built

Borwon

MBSP5A Connectivity Trials with Optus

FSG is proud to partner with the Commonwealth Government and Optus under MBSP5A to conduct two connectivity trials in Western Queensland.

Under the program, FSG will build and operate its 4G Network (Regional Australia Network™) to undertake two trials:

  • Active Neutral Host RAN–Delivery of one set of electronics and antennas on a site to facilitate coverage for the FSG Regional Australia Network™ and Optus 4G Network (Noting that capability would also be for Telstra, TPG, NBN Co and future Public Safety Mobile Broadband networks should they choose to participate in a trial). The trial will take place on a 196km stretch of the Adventure Way between Cunnamulla and Thargomindah in Queensland. All sites are under build.
  • Inbound Roaming –Ability for Optus mobile users to access the FSG Regional Australia Network™ and operate theirmobiles for voice and data services south east of St George at Kinsale and Nindigully.

Active Neutral Host RAN Trial Proposed Coverage

Roaming Trial Area

St George, QLD

Nindigully, QLD

FSG has completed the build, and the site is now broadcasting the FSG Regional Australia Network™. The FSG team has been putting the site through its paces and is pleased with the coverage and services, including the famous Nindigully Hotel. Shortly, both Optus and FSG engineering teams will hit the road and commence technical testing of the service – stay tuned for more details!

Coverage Disclaimer:  Coverage shown is indicative only and may be subject to change as site acquisition progresses. Local conditions such as terrain and vegetation whilst using a mobile device indoors or within a vehicle can impact the coverage your device receives and, thus, your ability to make and receive calls or use data.

Appletrees

FSG has completed the build, and the site is now broadcasting the FSG Regional Australia Network™.  The FSG team has been putting the site through its paces and is pleased with the coverage and services, including the famous Nindigully Hotel.  Shortly, both Optus and FSG engineering teams will hit the road and commence technical testing of the service – stay tuned for more details!

 

 

State

RFNSA ID

Site Name

Status

Site Type

Indicative Rollout Timeline

QLD

4492016

Thargomindah Town

Site is now stood.

FSG R.A.N equipment to be deployed. New solar power array footings completed.

Equipment being dispatched to the region.

Active Neutral Host RAN

Jun-24

QLD

Eulo

Site Acquired. Land clearing completed with construction to
commence Q2 2024. Towers delivered to Cunnamulla holding yard.

Active Neutral Host RAN

Jun-24

QLD

4490020

Waihora

Site is now stood. FSG R.A.N equipment to be deployed. New solar power array footings completed.

Equipment being dispatched to region.

Active Neutral Host RAN

Jun-24

QLD

Cunnamulla to Thargo - Paroo Side

Site Acquired. Land clearing is completed, with construction

commencing Q2 2024.

Towers delivered to Cunnamulla holding yard.

Active Neutral Host RAN

Jun-24

QLD

Cunnamulla to Thargo - Bullo Side

Site Acquired.

Land clearing is completed, construction commencing Q2 2024. Towers delivered to Cunnamulla holding yard.

Active Neutral Host RAN

Jun-24

QLD

West Lake Bindegolly

Site under build. Land cleared and tower assembled. Foundations
work to commence shortly.

Active Neutral Host RAN

Jun-24

QLD

Dynevor Downs

Site under build. Land cleared and tower assembled. Foundations
work to commence shortly.

Active Neutral Host RAN

Jun-24

NSW

Kinsale

Site now under build.

4G Roaming Site

TBC

NSW

TBC

Nindigully

Site built and under engineering testing.

4G Roaming Site

Jun-24

 

West Lake Bindegolly

Image 1

Dyvenor Downs

Image 2

Details about Mobile Deployment Code
Field Solutions Group, as a Carrier under the Telecommunications Act 1997, must comply with the Mobile Phone Base Station Deployment Industry Code C564:2020 when selecting a site and designing and operating Mobile Phone Radiocommunication infrastructure.
The Mobile Phone Base Station Deployment Industry Code is designed to:

  • allow the community and councils to have greater participation in decisions made by Carriers when deploying mobile phone base stations and
  • provide greater transparency to local communities and councils when a Carrier is planning, selecting sites for, installing and operating Mobile Phone Radiocommunications Infrastructure.

For further information on the Mobile Phone Base Station Deployment Industry Code, please click on the following link:

Communications Alliance – C564:2020 Mobile Phone Base Station Deployment (commsalliance.com.au)

To comply with the Mobile Phone Base Station Deployment Code, Field Solutions Group must provide detailed information about any proposed Mobile Phone Radio communications Infrastructure via the Radio frequency National Site Archive (RFNSA) website. Please follow the link below and enter the RFNSA Site ID number provided in the site lists above/below for detailed information.

https://www.rfnsa.com.au

Our Clients include

Field Solutions Group (FSG/ASX)